Georgetown's Planning and Zoning Commission unanimously recommended denying a rezoning request Tuesday night for a data center in northeast Georgetown. Residents packed council chambers, the lobby and the sidewalk, and more than 100 people signed up to speak.
The proposed data center by the numbers
- 28 acres
- proposed for rezoning near East University Ave.
- 100+
- people signed up to speak Tuesday
- 68 megawatts
- the proposed data center's size
- $10-15 million
- a year in property taxes, per the developer's representative
Speakers raised concerns about noise, water use, power reliability and the effect on nearby neighborhoods. Boz Sabeti, president of the Riverhill Homeowners Association, said, "I want to see people that are working for us and not for developers." Developer representative Phillip Niels said the project would be Georgetown's largest taxpayer. Earlier Tuesday, the Statesman reported that nearby residents had transparency questions.
- Proposal: one data center called Inner Loop Exchange, with on-site generators
- Developer says: low-level lighting, designed to limit noise
- Next step: City Council is expected to consider it Dec. 8
- To overturn the denial: council needs a 6-1 vote
The rezoning would raise the maximum footprint from 5,000 to 290,000 square feet
Floor area of the maximum allowed footprint, beside places you know
5 football fields would fit inside the maximum allowed footprint
Source: KEYE
View as table
| Floor area | |
|---|---|
| The maximum allowed footprint | 290,000 sq. ft. (up from 5,000 square feet) |
| A football field | 57,600 sq. ft. (end zones included) |
| A Walmart Supercenter | about 180,000 sq. ft. |
Tuesday's vote isn't the last word: the proposal is not yet officially rejected.